Following on from a meeting with Simon, Ed, and Bryan. It seems like
we’re trying to answer two questions:
Where are we overloaded?
What aren't we using? (That we should look to find or fit work to.)
Different contexts:
Managing current load
Always starts with released shop orders.
Would typically also include planned shop orders and requisitions.
Asks questions like:
Which work centres are overloaded? When? How much?
What is the load? (Released orders, planned orders, reqs, etc.)
When can the load be re-scheduled on the same work center?
(Can the load be pulled forward or pushed back? How much by?)
Can the load be moved to a different work center? Which? When?
(Identify alternates by production line.)
The trouble here is that the more questions you start asking the more
you realize that you are duplicating the work of a finite scheduler.
Ultimately that’s what the goal appears to be: manually finite
schedule those areas of the infinite schedule that indicate a capacity
constraint. Surely we should just invest our energy into getting a
workable finite schedule instead?
Wherever possible we should quantify the load in human terms such as
days, weeks, "shifts", etc. and not merely in pure numbers of hours.
Planning for future load
Forecast based
Aspects:
Production lines
Customers
Projects
Standard Names?
Work Centers with Interesting Consumption Patterns
In all cases we can assume that we have n jobs to schedule across m
(> 2) resources with multiple, sequential, operations utilizing
different resources to perform per job.
As a rough guide we have ~150 resources (active internal work centers)
and ~2000 shop orders with ~21000 operations to schedule. Slightly under
half of those orders are planned (~900) but as at the time of writing
account for only a third of the operations (~7000.)
There are an ~300 unconverted requisitions which could account for ~3200
more operations.
So, this is already a large dataset without the addition of multiple
customer forecasts.
Infinite Scheduling
Generally quite simple. The only constraints are the sequence of
operations per job, resource availability (non-working times), and the
maximum number of hours per operation on each resource.
It’s also a task that is easy to parallelize as each job can be
scheduled in isolation.
Both backward and forward scheduling are equally valid and can be mixed.
Different job sets can be easily, and commutatively, combined using
standard aggregations.
The data is fairly static and there is minimal “churn” resulting from
new loads (or changes to existing loads) as there is no interaction
between jobs.
There is no definite requirement to re-schedule jobs due to the progress
of time however it would almost certainly be useful to be able to both
see which jobs are overdue (have operations scheduled in the past) and
to forward schedule them (being advised of the new finish date.)
Additional data provides no real utility. This isn’t so much a
scheduling algorithm as it is an aggregation. Details of alternative
resources, for example, have far more utility when interpreting and
acting upon the results of the schedule than they do during the
scheduling process.
Outcomes
Overdue indication for jobs (when backward scheduling if an operation
is scheduled earlier than the current date then there is no means of
achieving the required date, likewise if forward scheduling and the
order does not finish before the required date.)
Resource over subscription (at potentially varying levels of detail.)
Essentially all an infinite schedule will give you is a heat map of
where your current scheduling results in resource over loading. This
could be produced at varying levels of detail both in time (daily,
weekly, etc.) and resource grouping (per work center, production line,
department, etc.)
This can then be used to manually adjust the loading by either altering
the assigned resources, changing the target dates, or modifying the
characteristics of the load (run times, etc.)
Finite Scheduling
By far the harder of the two problems and generally considered to be a
NP-Complete problem. Your results will always be an estimate and never
an “optimal” solution.
Genetic Algorithms are particularly well suited to
providing solutions and provide significant opportunity for parallelism.
Constraint or Logic based programming also provide useful frameworks for
writing scheduling algorithms.
Forward scheduling is by far the more sensible approach. Backward
scheduling really doesn’t make a lot of sense.
Different job sets can’t be combined but must instead be layered:
using the calculation of one set as an input/constraint for the
calculation of another.
Most changes to the input data will require significant if not total
recalculation. Something as simple as changing the resource assigned to
an operation or its run time will have significant knock-on effects.
The result should be recalculated periodically in order to stay
relevant. Once per day would probably be sufficient.
Finite scheduling is better suited to running against multiple
constraints such as both machine and labour availability. If you are
only interested in modeling a single set of constrained resources (i.e.
work centers) then an infinite schedule satisfies the 80/20 rule and
requires significantly less effort. However, as the number and
complexity of constraints increases so does the complexity of the
calculation and finite capacity scheduling ceases to be more complex and
so becomes the better model (as it produces more “accurate” results than
infinite scheduling.) I would argue that this point is crossed by simply
including labour scheduling alongside work center scheduling.
Unsurprisingly then, finite scheduling benefits greatly from additional
data that provides more specificity in the requirements and details of
potential alternatives. The more data that is available to the
algorithm the better the resulting schedule will be.
Outcomes
Easy to produce list of late orders.
Resource bottlenecks can be identified by average operation queue
time.
Provides the ability to produce accurate “best end dates” for new
requirements (due date quoting.)
It seems like finite scheduling provides relatively little extra benefit
over infinite scheduling given the very significant increase in
complexity however accurate quoting at point of sale is practically a
business imperative now.
Inputs
Which we have:
Material procurement constraints (e.g. maximum lead time of
unavailable material for an order.)
Rough order priorities (weighted priority based on need date.)
Which we don’t have and would improve the schedule:
Precedence of shop orders relative to one another (e.g. parent
assembly order to sub assembly orders.) Replaces order priorities with
exact sequence/dependency information.
This could be derived from MRP but the lack of links between
supplies and their consuming demands in IFS necessitates producing
such data ourselves.
Potential operation overlap details.
Distinct setup and run times.
Which would be required for scheduling labour:
Labour classes and employee assignments sufficient to provide the
“pools” of workers suitable for each operation.
An alternative that could be used would be to group employees by work
center based upon the work centers they’ve booked against recently
(e.g. the last six months.)
Actual labour run times for operations, distinct from the machine run
time.
Crew size requirements (e.g. for assembly ops requiring more than one
person)
In reality there is nothing preventing us from scheduling against labour
constraints at present. The above would all make the input data more
accurate and therefore improve the quality of the schedule but none of
them are required (except the grouping of employees and identification
of group(s) suitable for operations but the work center based grouping
would be sufficient to start with.)
Scheduling labour would also require a change to how we view work center
resource availabilities. At present the work center availabilities are
based on a rough approximation of the labour availability for that
work center. A schedule derived from the constraints of actual labour
availability and the labour derived work center availabilities would be
quite severely hindered in it’s utility.
Therefore when labour is used as a scheduling constraint the work center
constraints should be relaxed to better reflect their nature as
machines/tools for the jobs. The only real constraints they impose is the
number of distinct resources that are available (i.e. the number of
concurrent jobs they can run) and periods of unavailability due to
maintenance.
Glossary
“makespan”—the total duration of the proposed solution, from the start
of the first job until the end of the last.
“flow shop”—a scheduling environment of n × m jobs where the
processing sequence is the same for all jobs.
“job shop”—a scheduling environment of n × m jobs where the
processing sequence may be different for different jobs.